The course covers administration techniques as well as procedures in the "Pre-Contract" phase of the project consisting of the FIDIC Client Consultant Service Agreement. It likewise covers the "Message Agreement" award stage, including all agreement monitoring self-control and also insurance claims management issues. This sensible course discusses and also illustrates making use of the FIDIC conditions of contract for building the "Construction Agreement". The course covers the 1999 Agreements books with highlights about the 2nd Edition. The program will allow participants to gain self-confidence in working with these records, whether they stand for employers, experts, or professionals.
Introduction and principles
Introduction to FIDIC
Background to FIDIC contracts
Harmonization based on the type of project
Features of the 1999 editions with highlights regarding the Second Edition
Forms
User-friendliness
Preparation of conditions of contract
The legal character of FIDIC conditions of contract
Relationship between FIDIC conditions of contract and legal systems
Risk analysis
Which form to use
Overview of the 1999 contracts
Construction contract
Main differences between the construction contracts
Clause 1: General provisions and general issues
Clause 2: The employer
Clause 3: The engineer
Clause 4: The contractor
Clause 5: Construction contract - nominated subcontractors Clause 5: Plant and design-build contract - design
Management of projects
Clause 6: Staff and labor
Clause 7: Plant material and workmanship
Clause 8: Commencement delays and suspension
Tests on completion
Clause 9: Tests on completion
Clause 10: Employer’s taking over; defects liability
Clause 11: Plant contract - tests after completion
Clause 12: Construction contract - measurement and evaluation
Clause 13: Variations and adjustments
Clause 14: Contract price and payment
Suspension and termination
Clause 15: Termination by employer
Clause 16: Suspension and termination by contractor
Risk, liability, and force majeure
Clause 17: Risk and responsibility
Clause 18: Liability and insurance
Clause 19: Force majeure
Clause 20: Claims, disputes, and arbitration
Inherent project risk
Contractor’s claims and employer’s claims; claims procedures
Disputes
Amicable settlement
Dispute adjudication board
Arbitration
Dates | Venues | Price | Details |
---|
Write a public review